Timeline and Schedule

Project Schedule Overview

New MMRHS Building Availability by High School Grade (if passed)

Timeline & MSBA Process Overview

Eligibility – Module 1

March 2022 – Statement of Interest Accepted
June 2023 – MSBA Accepted MMRHS into the Feasibility Program


Forming the Project Team – Module 2

September 2023 – OPM Hired (Skanska USA Building, Inc.)
February 2024 – Design Team Selection (DiNisco Design, in collaboration with William Rawn Associates)


Feasibility Phase – Module 3

February 2024 – December 2024 – Feasibility Study Development
July 2024 – Preferred Design Program (PDP) due to MSBA
December 2024 – Preferred Schematic Report (PSR) due to MSBA
February 2025 – MSBA PSR Approval Meeting


Schematic Design Phase – Module 4

January 2025 – July 2025 – Schematic Design Development
July 2025 – Schematic Design (SD) Report due to MSBA
August 2025 – MSBA Project Scope Budget Approval Meeting


Funding the Project – Module 5

November 4th, 2025 – Local vote to approve project funding


Detailed Design – Module 6  (continues only if local vote passes)

Fall 2025 – Spring 2027


Construction – Module 7

Spring 2027 – Summer 2029

Spring 2027 Construction Starts

Fall 2029 Building Complete/Students Move-In

Summer 2030 Final Sitework Complete