Timeline and Schedule

Current Project Schedule

November 4, 2025, Local Vote (Approved!)

November 2025 – May 2026, Design Development Phase

May 2026 – Spring 2027, Construction Documents Phase

Spring 2027, Construction Bidding

Summer 2027, Construction Starts

Fall 2029, Building Opens

Summer 2030, Final Sitework Complete

 

 

MSBA Timeline & Process

Eligibility – Module 1

March 2022 Statement of Interest Accepted
June 2023 MSBA Accepted MMRHS into the Feasibility Program


Forming the Project Team – Module 2

September 2023 OPM Hired (Skanska USA Building, Inc.)
February 2024 Design Team Selection (DiNisco Design, in collaboration with William Rawn Associates)


Feasibility Phase – Module 3

February 2024 – December 2024 – Feasibility Study Development
July 2024 Preferred Design Program (PDP) due to MSBA
December 2024 Preferred Schematic Report (PSR) due to MSBA
February 2025 MSBA PSR Approval Meeting


Schematic Design Phase – Module 4

January 2025 – July 2025 – Schematic Design Development
July 2025 Schematic Design (SD) Report due to MSBA
August 2025 MSBA Project Scope Budget Approval Meeting


Funding the Project – Module 5

November 4th, 2025 – Local vote to approve project funding


Detailed Design – Module 6

Fall 2025 – Spring 2027


Construction – Module 7

Spring 2027 – Construction Bidding

Summer 2027 – Construction Starts

Fall 2029 – Building Complete/Students Move-In

Summer 2030 – Final Sitework Complete