Timeline and Schedule
Current Project Schedule
November 4, 2025, Local Vote (Approved!)
November 2025 – May 2026, Design Development Phase
May 2026 – Spring 2027, Construction Documents Phase
Spring 2027, Construction Bidding
Summer 2027, Construction Starts
Fall 2029, Building Opens
Summer 2030, Final Sitework Complete

MSBA Timeline & Process
Eligibility – Module 1
March 2022 – Statement of Interest Accepted
June 2023 – MSBA Accepted MMRHS into the Feasibility Program
Forming the Project Team – Module 2
September 2023 – OPM Hired (Skanska USA Building, Inc.)
February 2024 – Design Team Selection (DiNisco Design, in collaboration with William Rawn Associates)
Feasibility Phase – Module 3
February 2024 – December 2024 – Feasibility Study Development
July 2024 – Preferred Design Program (PDP) due to MSBA
December 2024 – Preferred Schematic Report (PSR) due to MSBA
February 2025 – MSBA PSR Approval Meeting
Schematic Design Phase – Module 4
January 2025 – July 2025 – Schematic Design Development
July 2025 – Schematic Design (SD) Report due to MSBA
August 2025 – MSBA Project Scope Budget Approval Meeting
Funding the Project – Module 5
November 4th, 2025 – Local vote to approve project funding
Detailed Design – Module 6
Fall 2025 – Spring 2027
Construction – Module 7
Spring 2027 – Construction Bidding
Summer 2027 – Construction Starts
Fall 2029 – Building Complete/Students Move-In
Summer 2030 – Final Sitework Complete